The Lovett School - Atlanta, Ga

Site work including Clearing, Demolition Grading and Drainage work for new Loop Road




  • Demolition involving demo of asphalt and concrete 47,000 sf., Modular Wall Demolition 1,140 lf.

  • Existing Storm Drainage Demolition 

  • Clearing 1.7 acres ,site prep to include export of excess fill dirt, excavation for soil nail wall 

  • Fine Grade and Backfill Curb 

  • Installation of 600 LF of Storm Drainage