Berry College - Mount Berry, GA

Site-work included erosion control, demolition, clearing, and grading.

  • Graded site to required elevations and specifications with necessary grading remediation. Exported and replaced unsuitable soils.

  • Storm and Secondary Drainage Systems: Installed 2,000 LF of pipe and secondary drainage pipe ranging in sizes 6" to 15"

  • Underground Detention Pond: Installed Ads Chamber System (ADS SC 740 ) with required fittings, fabric, and stone bedding.

  • Sewer System: Installed 140 LF of 6" sewer line with a 50 gallon Zurn Z-1185 Lint Interceptor.

  • Fire Lines: Installed 140 LF fire line pipe ranging in sizes of 4" to 8".

  • Domestic Water Pipe: Installed 60 LF of 4" domestic water pipe.

Project Gallery

OFFICE

120 Riverside Dr SW, Cartersville, GA 30120

Hours:

Monday through Friday

8am-5pm

INQUIRIES

For any inquiries, questions or commendations:

Call: (770) 606-9555

Email: Enda@cumminsenterprises.com

  • LinkedIn
  • Instagram
  • Facebook
excavator

© 2025 by Cummins Enterprises Inc. All rights reserved.

bottom of page