Cambridge Square - Brookhaven, GA
Redevelopment of existing retail shopping center. Construction of a New Publix
Building and Slab Demolition: We demolished 45,770 SQ FT. of building and slab, clearing the site for new construction and infrastructure installation.
Asphalt Demolition: Our team demolished 194,880 SQ FT. of asphalt, preparing the site for further development and ensuring a smooth transition for the next construction phases.
Grading and Dirt Work: We graded 2,355 CY of dirt to prepare the site for infrastructure installation, ensuring proper elevation and leveling for efficient drainage and construction.
Dirt Exporting: We exported 9,250 CY of dirt to maintain the required site grade and provide a clean, level foundation for future development.
Roof Drain Installation: We installed 860 LF of 10-inch HDPE pipe for roof drainage, ensuring that water is effectively managed and directed away from the building's foundation.
Storm Drainage System Installation: Our team installed various sizes of HDPE storm drain pipes to manage stormwater runoff efficiently:
405 LF of 18-inch HDPE
310 LF of 24-inch HDPE
320 LF of 30-inch HDPE
322 LF of 36-inch HDPE
32 LF of 36-inch Class III RCP
Storm Structures Installation: We installed 14 storm structures to ensure optimal water flow and effective stormwater management.
Underground Detention System Installation: We installed a Stormtrap underground detention system, consisting of 154 pieces, to effectively control and manage stormwater runoff, reducing the risk of flooding and ensuring compliance with environmental standards.
Infiltration Line Installation: We completed the installation of an infiltration line to enhance the stormwater management system and support groundwater recharge.
Sanitary Sewer Installation: Our team installed 826 LF of PVC sanitary sewer piping, ensuring a reliable and efficient wastewater management system.
Grease Trap Installation: We installed four 1,500-gallon grease traps to treat waste from food operations, ensuring compliance with environmental and health regulations.
Water Line Installation: We installed 60 LF of copper type 'K' domestic water line to provide a reliable water supply to the site.
Fire Water Line Installation: To enhance safety, we installed 200 LF of fire water line, sized with 51 Class DIP, to support the site's fire suppression system and ensure proper emergency response capabilities.